Commissioning Overview

All sensors need to be calibrated (Commissioned) after they are installed and before they can start collecting data. 

 

When should Commissioning happen?

Sensor commissioning should only happen once:

  • All sensors and hubs have been installed
  • After the furniture has been installed
  • At a time when the space is not occupied by many people, ideally empty 

 

What is required for Commissioning?

  1. Installer Credentials
  2. Laptop with internet
  3. Laser Distometer
  4. Plans with sensor ID Marked on locations
  5. Camera for photos of sensor locations